RAWY
2017
Design, manufacture and installation of cookies machine

DILAVE
2016
Electrical installation engineering

NESTLE
2016
Supply of mechanical labor for maintenance
Maintenance service for gas boiler.

UTE
2015
Hydraulic design and calculation of local fire installation management of works.

NESTLE
2015
Packaging line electromechanical modifications
Design and installation of safety protections for packaging line machines.

GERDAU
2015
Design and installation of ground electrical protection for new warehouse for lamination line.
Installation of low voltage electrical installation and lighting for new warehouse for lamination line.

NESTLE
2014
Relocation of electromechanical equipment for thermal conditioning.

BONSET
2014
Mechanical and electrical assembly of new line of Production of PET.

F.N.C.
2013
Installation of new carbon filters in Montevideo plant.
(Pentair Water Latinoamericana).

NESTLE
2013
Installation of sanitary hot water circuit system for vests.

ARROZUR
2013
Mounting hexane pipes from ½ "to 8". Reform of pre-cleaning equipment and reception of rice.

Cristalpet do Brasil
2013
Engineering manangment of station of 69 kV, 20 MVA:
High voltage equipment, protection system, remote control system, telemetering system, 2 Km of 69 kV airline.

COMPAÑÍA SALUS
2012
Relocation and layout modification of equipment in bottling lines 1 and 2.

FRIGORIFICO PUL
2012
Manufacture and assembly of structures and pipelines new ammonia and water cooling system.